KITUI COUNTY

Constituency

Project

Components

Area in acres

Crops grown

Status

Kitui Central

Construction of Kalundu phase I Irrigation project

i)Construction of 2 tanks of capacity 325 m3  

(ii)  Pipeline establishment   (iii) Supply and Installation of 1/2 acre drip systems 200 No.

100

Maize & horticulture

Project completed but requires installation of electricity for production to commence

Kitui Central

Construction of Kalundu phase II Irrigation project

Construction of 1 tanks of capacity 353 m3, pump house and sump, pump supply and installation, supply of electricity to pump house, pump line establishment

25

Maize & horticulture

Project completed awaiting the installation of power to start production

Kitui Rural

Kivisuni Irrigation Project phase 1

(i)   Supply of 30 tanks of capacity 10 m3 and construction of 30 stands (ii) Pipeline establishment (iii) Construction of 30 shallow wells (iv) Supply and Installation of 1/4 acre drip systems 300 No.

100

Maize & horticulture

 Under production

Kitui Rural

Kasivuni Irrigation Project Phase 2

(i)   Supply of 30 tanks of capacity 10 m3 and construction of 30 stands (ii) Pipeline establishment (iii) Construction of 30 shallow wells (iv) Supply and Installation of 1/4 acre drip systems 200 No.

300

Maize & horticulture

Under production

Kitui Central

Kitui clusters boreholes

Drilling of borehole and equipping water

10

Tomatoes

Under production

Kitui Central

Wingo Irrigation Project

Construction of shallow wels, construction of stands, water

10

Maize & horticulture

Under production

Mutitu

Ngomano Irrigation Project Phase I

(i)   Supply of 30 tanks of capacity 10 m3 and construction of 30 stands (ii) Pipeline establishment (iii) Construction of 30 shallow wells (iv) Supply and Installation of 1/4 acre drip systems 400 No.

100

Maize & horticulture

Under production

Mutitu

Ngamano Irrigation Project Phase II

(i)   Supply of 40 tanks of capacity 10 m3 and construction of 30 stands (ii) Pipeline establishment (iii) Construction of 40 shallow wells (iv) Supply and Installation of 1/4 acre drip systems 300 No.

75

Maize & horticulture

Under production

Mwingi North

Usueni Irrigation Project Phase I

Construction of pump house, 6km electric fence,5No receptor basins, lining of 3km canals, mainline pipe, installation of 5 pumps, supply of electricity, bush clearing 500 acres

500

Maize & horticulture

Under production

Mwingi North

Usueni  Irrigation Project Phase II

Construction of intake canal, sump, mainlines, sub-mainlines, distribution network and infield system for 500 acres and bush clearing for 500 acres

500

Maize & horticulture

Awaiting completion of infield system to commence production